Hardy’s contract totaled just under $5,000,000 for this 136,000 SF Hospital. Design Build services were provided for the POB portion of the building (88,000 SF). All HVAC equipment was provided and installed by Hardy including 225,000 pounds of duct, (2) 350 ton chillers, (2) 70 ton cooling towers, (8) pumps, (2) 125 HP Boilers and (6) Steam sterilizers.
“Hardy Corporation is currently performing projects in several areas of the hospital and we are pleased with their dependability and workmanship.” John S. Taylor, Facility Maintenance Manager, St. Vincent’s Hospital