UAB Central Utilities Plant #5, Chiller #2

Birmingham, AL

Hardy executed this project as the prime contractor directly with UAB. The mechanical portion was self performed while 8 trade companies (structural, electrical, roofing, concrete, instrumentation, etc) worked under Hardy has subcontractors. The mechanical portion of the project included (1) 4,000 ton chiller, (1) 8,000 gpm pump, (1) 12,000 gpm pump, (4) cooling towers, and (2) 36” chilled water lines which had to be installed underground to the existing campus chilled water loop.